ISS – B90 CRU System

SOL Services were appointed by ISS to undertake critical remedial and replacement works to the B90 CRU system, including associated condensate and steam infrastructure within a GRP enclosure and wider B61a service yard.

The existing system had been non-operational due to incomplete commissioning by a previous contractor, who went into administration approximately
4–5 years prior, leaving the system unable to return condensate effectively.

Overview

Client Benefits

  • Full reinstatement of a previously non-operational CRU system
  • Improved reliability and efficiency of condensate and steam management
  • Safe removal and reconfiguration of legacy failed infrastructure
  • Enhanced service yard layout with newly infilled and usable space
  • Minimal disruption through use of temporary steam